Due dateDelivery dateType
1D1.1 Report on national ACTRIS consortia4039Report
2D1.2 Report on enhancement of community building4646Report
3D1.3 Report on engagement activities4646/51Report
4D1.4 Status report on regional developments and sustainability plans4646Report
 

Work Package 2

   
5D2.1 Contingency plan for implementation (confidential) 1221Report
6D2.2 Report on financial and capacity scenarios4048Report
7D2.3 List of ACTRIS policies, internal rules and legal agreement templates4646Websites, patent fillings, videos etc.
8D2.4 Updated ACTRIS Business Plan4646Report
9D2.5 Final report on validation of ACTRIS operation support and service provision4848Report
 

Work Package 3

   
10D3.1 Draft innovation strategy2424Report
11D3.2 Strategic plan to enhance national and regional ACTRIS activities3638Report
12D3.3 The impact of ACTRIS on society: outcome of a Contingent Valuation study4041Report
13D3.4 ACTRIS strategy on scientific added value, impact, attractiveness and relevance4242Report
 

Work Package 4

   
14D4.1 Descriptions of the workflows between ACTRIS components69Report
15D4.2 Report on internal organization of CFs2424/42Report
16D4.3 Revised CF implementation plans2424Report
17D4.4 Revised ACTRIS Data Management Plan4647Report
18D4.5 Report on CF human capital building4646Report
19D4.6 Report on testing activities at CFs, outcomes and identified optimization actions4848Report
 

Work Package 5

   
20D5.1 ACTRIS NF Labelling Plan1818Report
21D5.2 Report on tests of RI operations at NFs and recommendations for improvements3643Report
22D5.3 Report on support activities for NFs and RPFs4444Report
23D5.4 Report on development, testing and implementation of new technologies4647Report
24D5.5 Report on training of NF and RPF operators4847Report
 

Work Package 6

   
25D6.1 ACTRIS Science and User Forum1016Websites, patent fillings, videos etc.
26D6.2 Report on the ACTRIS User support system1818Report
27D6.3 ACTRIS online Catalogue of Services2024Websites, patent fillings, videos etc.
28D6.4 Updated ACTRIS User strategy4548Report
29D6.5 ACTRIS Access and Service Management Plan4848Report
30D6.6 ACTRIS Access Management Platform4847Websites, patent fillings, videos etc.
 

Work Package 7

   
31D7.1 Recommendations for optimizing the access process and user interaction2729Report
32D7.2 Recommendations for implementing access to ACTRIS services4648Report
 

Work Package 8

   
33D8.1 Report on planned joint activities and synergies with other RIs and e-RIs1826Report
34D8.2 Defining the needs for EOSC resources in ACTRIS2439Report
35D8.3 Assessment of ACTRIS contribution to, and alignment of ACTRIS policies with, international networks and initiatives, incl. GEOSS and COPERNICUS (confidential)2432/42Report
36D8.4 Summary report on international ACTRIS training courses4041Report
37D8.5 Application to GEO initiative on short-lived climate species4848Report
 

Work Package 9

   
38D9.1 Progress Report on the position of ACTRIS in the European Innovation Ecosystem1818/48Report
39D9.2 Means and recommendations for the operation of the ACTRIS liaison office3636Report
40D9.3 Report on the results of the flagship actions4848Report
41D9.4 ACTRIS innovation offer portfolio4848Websites, patent fillings, videos etc.
 

Work Package 10

   
42D10.1 Updated plan for communication within ACTRIS1212Report
43D10.2 Creation of dedicated communication portfolio1618Websites, patent fillings, videos etc.
44D10.3 Communication and public relations strategic master plan4242Report
45D10.4 Updated plan of exploitation and dissemination of the results4848Report
 

Work Package 11

   
46D11.1 Ethics compliance in work performed outside EU22Report
47D11.2 Protocols for questionnaires in ACTRIS IMP44Report
48D11.3 ACTRIS IMP data management plan66Open Research Data Pilot
49D11.4 Minutes of ACTRIS IMP meetings in 20201412Report
50D11.5 Minutes of ACTRIS IMP meetings in 20212623Report
51D11.6 Minutes of ACTRIS IMP meetings in 20223835Report
52D11.7 Analysis of gender balance in ACTRIS4241Report
53D11.8 Minutes of ACTRIS IMP meetings in 20234847Report
54D11.9 Report on associated partnership program4847Report
 

Work Package 12

   
55D12.1 H - Requirement No. 1 (confidential)66Ethics requirement
56D12.2 POPD - Requirement No. 2 (confidential)66Ethics requirement

 

#

Work Package 1

Due dateDelivery date
1MS1.1 Updated list of National ACTRIS consortia with National Contact Persons33
2MS1.2 First IAC meeting held during ACTRIS IMP82
3MS1.3 First SIAB meeting held during ACTRIS IMP123
4MS1.4 First ACTRIS community meeting held183
5MS1.5 First regional meeting organised1811
 

Work Package 2

  
6MS2.1 Methodology and criteria for validation of ACTRIS operation support and service provision1224
7MS2.2 Negotiations started with the Central Facilities1818
8MS2.3 Plan for ACTRIS personnel training and human capital development1817
9MS2.4 Mid-term report on ACTRIS operation support and service validation2424
10MS2.5 Draft report on financial and capacity scenarios2429
11MS2.6 Refined risk management plan2425
 

Work Package 3

  
12MS3.1 ACTRIS meeting on technologies and innovation with participation of the ACTRIS associate from private sector1217
13MS3.2 Macroeconomic impact analysis updated1824
14MS3.3 ACTRIS Meeting with the National Stakeholders organized2025
15MS3.4 ACTRIS general science meeting focusing on the user dimension and the international stakeholders2429
 

Work Package 4

  
16MS4.1 Release of the tool for estimating the necessary capacity at the Central Facilities33
17MS4.2 Recommendations for harmonisation of procedures and tools across the ACTRIS domains1212
18MS4.3 Selection of web-based NF-TC-DC workflow management tool1218
19MS4.4 Action plan for CF human capital building1214
20MS4.5 Release of the list for priority operation support and services1216
21MS4.6 Access to first version of web-based NF-TC-DC workflow management tool2434
22MS4.7 Collection of the first feed-back on the operation support provided to National Facilities3642
 

Work Package 5

  
23MS5.1 Exercises to test RI operations at experienced NFs defined1218
24MS5.2 First series of NF thematic workshops on remote sensing, in-situ measurements and simulation chamber experiments performed1414
25MS5.3 First NFs labelled and operational2436
26MS5.4 Connections to new NFs and RPFs established2626
27MS5.5 First series of NF technical workshops on new developments for the observation of aerosol, clouds and reactive trace gases performed2628
28MS5.6 Majority of NFs labelled and operational4848
29MS5.7 New NFs and RPFs reached the level of ACTRIS standards4848
 

Work Package 6

  
30MS6.1 ACTRIS User experience map616
31MS6.2 Detailed description of ACTRIS Service catalogue613
32MS6.3 Design, features and functional requirements of the ACTRIS Science and User Forum813
33MS6.4 1st release of the ACTRIS online Catalogue of Services1018
34MS6.5 2nd draft of the ACTRIS Management Plan1212
35MS6.6 Updated analysis of user needs1518
36MS6.7 Enhanced user strategy with recommendations to ACTRIS facilities1839
37MS6.8 Beta version of the Access Management Platform2226
38MS6.9 Results of the testing of the access and services provision system4242
 

Work Package 7

  
39MS7.1 Definition of the pilot access process to ACTRIS facilities812
40MS7.2 Advertisement and launch of first call for access911
41MS7.3 Advertisement and launch of second call for access2121
42MS7.4 Intermediate assessment of the pilot access concept and process2527
43MS7.5 Advertisement and launch of third call for access3331
44MS7.6 Final assessment of the pilot access concept and process4448
 

Work Package 8

  
45MS8.1 Identification of potential synergistic activities with other ENVRIs66
46MS8.2 A first evaluation of alignment of ACTRIS with international networks624
47MS8.3 Meetings with international stakeholders addressing joint global initiatives and focusing on connection with GCOS916
48MS8.4 Internal evaluation of the potential use of e-infrastructure portfolio by ACTRIS1224
49MS8.5 First International ACTRIS training course held1217
50MS8.6 Series of meetings with international stakeholders achieved that serve the purpose of an application to GEO initiative2426
 

Work Package 9

  
51MS9.1 Launch of survey to identify past and current collaboration between ACTRIS and private sector and success stories611
52MS9.2 Identification of collaboration models between ACTRIS and private sector1216
53MS9.3 Recommendations to ACTRIS facilities1835
54MS9.4 Draft ACTRIS Innovation offer portfolio2424
55MS9.5 Design of the ACTRIS Innovation section in the ACTRIS web-site2627
 

Work Package 10

  
56MS10.1 Analysis report on the performance and fitness of the internal communication610
57MS10.2 Report of the communication means used and success, incl. metrics1010
58MS10.3 Guidelines for communication and public relations2424
59MS10.4 Analysis of the best practices to engage ACTRIS user groups3232
60MS10.5 Updated report of the communication means used and success, incl. metrics3839
 

Work Package 11

  
61MS11.1 Deliverable work flow description available33
62MS11.2 ACTRIS IMP kick-off meeting33
63MS11.3 Procedures for associated partnership program available33
64MS11.4 Internal communication channels set up44
65MS11.5 ACTRIS IMP meeting 20212415
66MS11.6 ACTRIS IMP meeting 20223628
67MS11.7 ACTRIS IMP final meeting4746

 

Meeting2024
ACTRIS Week 2024, November 5-7, Matera, ItalyAgenda - List of Participants - Action Items - Presentations
Meeting

2023

ACTRIS Week 2023, October 24-27 2023, Heraklion, GreeceAgenda - List of Participants - Action Items - Presentations
Meeting

2022

ACTRIS Week 2022, October 24-27 2022, Prague, Czech RepublicAgenda - List of Participants - Action Items - Presentations
2022 Spring ACTRIS IMP Meeting, April 20-21 2022, virtualAgenda - List of Participants - Action Items - Presentations
Meeting

2021

ACTRIS Week 2021, October 27-29 2021, virtualAgenda - List of Participants - Action Items - Presentations
2021 Spring ACTRIS IMP Meeting, March 29-30 2021, virtualAgenda - List of Participants - Action Items - Presentations
Meeting

2020

ACTRIS Week, October 26-28 2020, virtualAgenda - List of Participants - Action Items - Presentations
ACTRIS NOx/VOC QA Workshop 2020, virtualAgenda - List of Participants - Minutes - Presentations
ACTRIS IMP Kick-Off Meeting, March 2-6 2020, Larnaca, CyprusAgenda - List of Participants - Action Items - Presentations