1 | MS1 Establishment of all interim ACTRIS governance bodies for implementation phase | 12 | 14 |
2 | MS2 Draft ACTRIS Business Plan | 30 | 32 |
Work Package 2 |
|||
3 | MS3 Outline of legal entity analysis | 3 | 5 |
4 | MS4 Workshop on relevant issues and outcomes from WP7 | 7 | 9 |
5 | MS5 Legal entity analysis report | 9 | 9 |
6 | MS6 Draft of ethical guidelines and preparation of other documents for Tasks 2.3 and 2.4 started | 12 | 18 |
7 | MS7 Draft of statutes and agreement template | 16 | 15 |
8 | MS8 Draft data policy, access and service policy and staff policy | 20 | 18 |
9 | MS9 Workshop on critical issues in documents | 24 | 21 |
10 | MS10 All documents ready for further discussions and decisions | 32 | 32 |
Work Package 3 |
|||
11 | MS11 Draft version of the costs book | 14 | 14 |
12 | MS12 Draft version of internal financial rules | 22 | 22 |
13 | MS13 Draft version of the financial plan structure and principles | 28 | 25 |
Work Package 4 |
|||
14 | MS14 Delphi survey | 6 | 5 |
15 | MS15 Scenario workshop 1 | 6 | 6 |
16 | MS16 Scenario workshop 2 | 9 | 9 |
17 | MS17 Preliminary estimate of CF operation costs | 10 | 11 |
18 | MS18 Call for applications for Central Facilities | 18 | 18 |
19 | MS19 CF implementation plan template | 32 | 32 |
Work Package 5 |
|||
20 | MS20 Draft of documentation on technical concepts and requirements for ACTRIS observational platforms | 12 | 12 |
21 | MS21 Draft of documentation on technical concepts and requirements for ACTRIS exploratory platforms | 12 | 12 |
22 | MS22 Draft documentation on ACTRIS National Facility labelling principles | 24 | 22 |
Work Package 6 |
|||
23 | MS23 Definition of user requirements | 12 | 36 |
24 | MS24 Draft report on access principles, management, and process | 18 | 18 |
25 | MS25 Access cost analysis performed | 20 | 36 |
26 | MS26 Definition of key performance indicators | 24 | 29 |
Work Package 7 |
|||
27 | MS27 Input on contractual agreement with third parties | 6 | 9 |
28 | MS28 Draft report for synergetic operations of European Environmental RIs | 12 | 12 |
29 | MS29 Draft procedures for establishing new CF in ACTRIS | 12 | 9 |
30 | MS30 Draft procedures for changing technical requirement in ACTRIS | 12 | 9 |
31 | MS31 Draft liaison recommendations | 18 | 21 |
32 | MS32 Draft partnership recommendation | 18 | 21 |
33 | MS33 Draft contractual agreement with third- party countries outside Europe | 24 | 35 |
34 | MS34 Draft recommendation for ICT development | 24 | 36 |
35 | MS35 Draft contractual agreements for service provision to European initiatives and networks | 30 | 29 |
Work Package 8 |
|||
36 | MS36 Preparation of the questionnaire | 9 | 7 |
37 | MS37 Identification of the user communities for the interviews | 20 | 20 |
38 | MS38 Identification of specific case studies as a starting point for quantifying ACTRIS monetary impact | 25 | 25 |
Work Package 9 |
|||
39 | MS39 ACTRIS PPP kick-off meeting | 2 | 2 |
40 | MS40 Associate Partnership forms and application process established | 3 | 6 |
41 | MS41 Establishment of quality assurance flow | 3 | 6 |
42 | MS42 First ACTRIS PPP annual meeting | 12 | 14 |
43 | MS43 Second ACTRIS PPP annual meeting | 24 | 29 |
44 | MS44 ACTRIS PPP final meeting | 36 | 35 |
Duis mollis, est non commodo luctus, nisi erat porttitor ligula, eget lacinia odio sem nec elit. Sed posuere consectetur est at lobortis. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Duis mollis, est non commodo luctus, nisi erat porttitor ligula, eget lacinia odio sem nec elit. Etiam porta sem malesuada magna mollis euismod.